Timeline

Our HomeBuilding Timeline

May 27, 2014 - Signed the original paperwork
May 30, 2014 - Met with NVR to sign paperwork

June 11, 2014 - Signed off on all structural changes
June 14, 2014 - Rite Rug appointment
June 16, 2014 - Guardian appointment

July 1, 2014 -  Final selectionss / Electrical / Exterior Colors appointment

August 7, 2014 -  Pre-Construction Meeting
August 11, 2014 - Ground-breaking & clearing of land
August 14, 2014 - Footer poured
August 18, 2014 - Basement concrete walls poured

Tentative move-in - Mid to late NOVEMBER 2014!!